  "createdAt": "2026-10-30T13:16:14+08:00",
  "eventKind": "water_project",
  "id": "event_beijing_tuanjiu_phase_2",
  "lang": "en",
  "revision": 8,
  "slug": "beijing-tuanjiu-phase-2",
  "sourceLang": "zh",
  "sources": [
    {
      "author": "北京市水务局网站（正文未署名）",
      "date": "2026-10-20",
      "id": "official",
      "title": "北京市南水北调团城湖管理处巡查值守项目-团城湖调节池工程、团九二期工程以及东水西调工程巡查值守项目公开招标公告",
      "url": "https://swj.beijing.gov.cn/zwgk/zfcg/zbgg/202610/t20261020_4911706.html"
    },
    {
      "author": "北京市水务局",
      "date": "2026-05-09",
      "id": "demand_2026",
      "title": "北京市南水北调团城湖管理处水利工程日常维修养护费-设备维修养护采购需求调查公告",
      "url": "https://swj.beijing.gov.cn/zwgk/zfcg/qtgg/202605/t20260509_4643727.html"
    }
  ],
  "status": "published",
  "summary": "A Beijing component of the South-to-North Water Diversion linking the Tuancheng Lake regulating pond with the No. 9 waterworks supply system.",
  "tags": [],
  "title": "Phase II of the Tuanjiu project",
  "type": "event",
  "updatedAt": "2026-10-30T14:07:45+08:00",
  "updatedBy": "user:admin"
}
---

# Phase II of the Tuanjiu project

A Beijing component of the South-to-North Water Diversion linking the Tuancheng Lake regulating pond with the No. 9 waterworks supply system.

Phase II of the Tuanjiu project links the Tuancheng Lake regulating pond with the No. 9 waterworks supply system. The section runs from the ring main outlet of the pond to the phase II control gate at the Longbeicun gate station, about 4 kilometres in total.

## Works

A 2026 procurement survey lists a water conveyance tunnel, the East-to-West transfer outlet, the Tuanbei intake gate station and air-release and drainage facilities along the route; the tunnel has an internal diameter of 4.7 metres and conveys water under gravity pressure. Design maximum flow is 28.3 cubic metres per second forward and 18.3 in reverse.[^demand_2026]

更新时间：2026-10-30

## 标签


## 关系

- Related announcements：[北京市南水北调团城湖管理处巡查值守项目-团城湖调节池工程、团九二期工程以及东水西调工程巡查值守项目公开招标公告](/en/works/beijing-water-notice-2026-10-20-tuanchenghu-tiaojiechi.html) 
- Occurred at：[Beijing](/en/places/beijing.html) 

第 1 / 1 页，共 2 条。

## 来源

- 北京市南水北调团城湖管理处巡查值守项目-团城湖调节池工程、团九二期工程以及东水西调工程巡查值守项目公开招标公告：https://swj.beijing.gov.cn/zwgk/zfcg/zbgg/202610/t20261020_4911706.html 
- 北京市南水北调团城湖管理处水利工程日常维修养护费-设备维修养护采购需求调查公告：https://swj.beijing.gov.cn/zwgk/zfcg/qtgg/202605/t20260509_4643727.html 